How long does someone have to file a mechanic's lien if a notice of completion or cessation was not filed by the owner?

  1. 30 days from completion of the work

  2. 60 days from completion of the work

  3. 90 days from completion of the work

  4. 120 days from completion of the work

The correct answer is: 90 days from completion of the work

The correct timeframe for filing a mechanic's lien when no notice of completion or cessation has been filed by the owner is 90 days from the completion of the work. This standard is part of California lien law, which is designed to protect contractors, subcontractors, and suppliers by allowing them a specific period to secure their right to claim a lien against a property for unpaid work. In this context, a mechanic's lien is a legal claim that can be placed on a property to ensure payment for services rendered. If a notice of completion or cessation is not filed, the extended period of 90 days allows those who provided work or materials to have ample time to file their lien, ensuring their rights are protected even without a formal notice from the property owner. The other timeframes listed are either too short or not aligned with the legal requirements established by California law regarding mechanic's liens.